March, 2022 - Hard to fix: a reminder of the importance of lifting subjects


  • Date: 24/03/2022
March, 2022 - Hard to fix: a reminder of the importance of lifting subjects

In the recent case of DHL Project & Chartering Ltd v Gemini Ocean Shipping Co Ltd [2022] EWHC 181 the Commercial Court held that the parties had not concluded a binding contract after conditions to which the charter party fixture was subject had not been ‘lifted’.  As a result, the arbitration agreement contained in the charterparty did not apply and the arbitration award was set aside on the basis that the arbitrator did not have jurisdiction.

The facts

In August 2020, DHL Project & Chartering Ltd (“the charterer”) and Gemini Ocean Shipping Co Ltd (“the owner”) entered into fixture negotiations for a voyage to carry coal from Newcastle, Australia to Zhousan, China on the ship “Newcastle Express”.  

On 25th August, 2020 the intermediary broker circulated a recap which reflected what had been agreed between the parties. The recap provided: “SUBJECT TO SHIPPERS/RECEIVERS APPROVAL WITHIN ONE WORKING DAY AFTER FIXING MAIN TERMS & RECEIPT OF ALL REQUIRED CORRECTED CERTIFICATES/DOCUMENTS” and “RIGHTSHIP INSPECTION WILL BE CONDUCTED ON 3RD/SEPT…”. It was important for the ship to be approved by Rightship for the proposed voyage and clause 2 of the recap also provided that the ship should be “RIGHTSHIP APPROVED” and should be so maintained throughout the duration of the voyage.

Between 1st and 3rd September, 2020 correspondence took place between the parties via brokers regarding arrangements for the Rightship inspection, with the owner confirming that the inspection would take place on 3rd September, completing on 4th September and the ship would sail on 5th September, 2020. The charterer asked if the inspection could take place sooner as the shipper would not accept the ship until Rightship approval had been obtained.  The shipper was concerned that the it was taking too long and, on 2nd September, 2020, requested the charterer to change the ship.

On 3rd September, 2020 the charterer sent a message to the broker stating “Shippers not accepting Newcastle Express due to Rightship not rectified, kindly consider this vessel free”.  The charterer sent a further message later that day advising that the shipper did not want to wait for rectification of the ship and “we hereby release the vessel due to Rightship and not holding her any longer”.

It was agreed between the parties that, at the time of these messages, the charterer had not provided its confirmation that there had been approval either by the shipper or the receivers and there was not a ‘clean’ fixture as the relevant ‘subject’ had not been lifted. 

However, the owner argued that there was a binding charter party between the parties and that the charterer was in repudiatory breach of the charter party following its emails on 3rd September, 2020. The owner brought a claim against the charterer in arbitration on the basis that clause 17 of the fixture recap provided for English law and arbitration in London. The arbitrator awarded the owner US$283,416.21 in damages for the charterer’s repudiatory breach of the charterparty.

Challenge to the Arbitration Award

The charterer challenged the arbitration award under section 67 of the Arbitration Act 1996 on the basis that the arbitrator lacked substantive jurisdiction because there was (1) no binding fixture and (2) no binding arbitration agreement between the parties. The fixture was agreed “on subs”, namely subject to shipper/receiver’s approval, and this was a precondition to any binding contract.  As the subject was never ‘lifted’, there was no binding contractual agreement, including no arbitration agreement, and the arbitrator did not have jurisdiction to make the award.

The owner contended that the parties expressly agreed to arbitration in London and there was a binding arbitration agreement between the parties at clause 17 of the fixture recap.  Whether there was a binding arbitration agreement is a separate question to whether there was a binding fixture. Under English law, an arbitration agreement is separate to the main contract such that the invalidity of the main contract does not prevent the arbitration agreement being enforced  (known as the ‘doctrine of separability’).  Therefore, the owner argued that the arbitrator did have jurisdiction to make the award.

Commercial Court judgment

Finding in the charterer’s favour, the court held that the fixture was not binding unless and until the charterer communicated that the “subject” was lifted.  In considering the contractual significance of the ‘subject’ provision, the court referred to the explanation of Foxton J in The Leonidas [2020] EWHC 1986 (a case where the UK Defence Club was involved for its owner Member) as follows:

When the main terms for charterparty have been agreed but the parties have yet to enter into contractual relations, this is generally referred to by shipowners, charterers and chartering brokers as an agreement on “subjects” or “subs”, an expression which signals that there are pre-conditions to contract which remain outstanding. The conclusions of a binding contract in respect of such an agreement is seen as dependent on the agreement of the relevant party or parties to “lift” (i.e. remove) the subjects.”

The court found that the ‘subject’ provision in this case, being shippers/receivers approval, was of the character described by Foxton J in The Leonidas and its commercial purpose was that the charterer did not wish to make a binding contract until both the shipper and the receiver had approved the ship. The effect of the ‘subject’ was to negate the charterer’s intention to enter into any contract at all, unless and until the ‘subject’ was lifted.

Furthermore, the placement of the provision at the start of the recap and the use of bold text reflected the importance of the provision and, in the court’s view, it qualified everything that followed, including the arbitration clause.  The arbitration agreement should not be regarded as a ‘mini-agreement’, divorced from the main agreement, but rather it is part of the “bundle of rights and obligations under negotiation, and all of those rights and obligations were subject to the “subject” clause.” Accordingly, the court held that the arbitrator had no jurisdiction and the arbitration award was set aside.

This decision reinforces that, generally, the court considers that subjects in fixture negotiations are pre-conditions to the conclusion of a binding contract. As such, parties need to be aware of what obligations need to be performed in order for the subjects to be ‘lifted’. 

Following the Commercial Court judgment, the owner was granted leave to appeal the decision and so we can expect to see a decision of the Court of Appeal on these issues in the near future.

As always, Members are invited to contact their usual Club contact for further advice in relation to the issues discussed above.


About the author:



Newsletter

Our newsletter update gives you insight into what's going on in the maritime industry

Subscribe

You are currently offline. Some pages or content may fail to load.